Nunspeet pedaal case
Behind the organ a seperate case for the large pedal stops is made. The case is already partly erected and the firsts pipes have taken their place.
For more picture click here.
Assembly organ Lunteren has started
The assembly works started on monday September 2nd.
week 1:
View the embedded image gallery online at:
http://vandenheuvel-orgelbouw.nl/en/?start=12#sigProId51769a9c1e |
week 2:
View the embedded image gallery online at:
http://vandenheuvel-orgelbouw.nl/en/?start=12#sigProIdafca843631 |
week 3:
View the embedded image gallery online at:
http://vandenheuvel-orgelbouw.nl/en/?start=12#sigProId987379ff8a |
week 4:
View the embedded image gallery online at:
http://vandenheuvel-orgelbouw.nl/en/?start=12#sigProId6cdcbd1dbd |
Nunspeet works
Behind the organ a seperate case will be constructed which houses newly made Prestant 16 of wood, the Octaaf 8 and the new Bazuin 16 constructed with full length wooden resonators. The existing pedal wind chest will be used for the remaing pedal stops.
Pictures of the crafting of the new Prestant 16 pipes and the Bazuin 16 resonators.
View the embedded image gallery online at:
http://vandenheuvel-orgelbouw.nl/en/?start=12#sigProIdcb4e0f6aec |
Dismantling organ Lunteren
The dismantling of the organ started on 17 June. Construction of the organ in the Church will start on 2 September.